General Installation Procedures
For all procedures Download PDF Version
STEP 1. |
|
|
STEP 2. |
|
|
| STEP 3. Fix profile to substrate aligning joints and securing it with props. Clean with scraper and press simultaneously the excess Cement Mixture. Blend in with a feathering motion utilising a sponge with clean water the excess of the mix. Allow 24 hours to set. |
|
|
| STEP 4. Remove all props and proceed to sand profile joints. |
|
|
| STEP 5. Screeding/Patching process: re-apply 2nd coat of DULUX AcraTex 500/6 Exsulite Render/Portland Cement Mixture to profile joints and seams. Blend in with a feathering motion utilising a sponge with clean water the excess of the mix. Allow 4 to 6 hours to set. |
|
|
| STEP 6. Clean up around profiles with a wet sponge for final touches. |
|
|
| STEP 7. Finalising the installation process proceed with the sealing/waterproofing and caulking expansion joints as per Typical Detailed Procedures. |
||